Colossal Load Marks Key Project Milestone

2024年7月18日
梅根摇

Mill Communications Coordinator

boiler delivery at cedar river mill

On a blustery spring morning in 2023, ceremonial shovels were dug into the dirt, symbolizing the groundbreaking of a significant International 纸 capital project, and one of the largest projects in Cedar River Mill’s history. Now, a year later, the project to build two natural gas power boilers is full steam ahead.

The $103 million investment began as many do with plenty of earth moving, underground pipe lament and prep work. With the groundwork complete, the next step was to lay the foundation.  

基础与支持  

超过11周, 大约5,350 cubic yards of concrete was poured, creating the six-and-a-half-foot thick foundation for the future boilers and water treatment. Approximately 535 trucks brought in the cement over five separate pour dates.  

The feat of this part of the project was massive. To ship something that is that heavy over the road, takes a large amount of engineering.

大家可以想象, the magnitude of these pours came with several planning obstacles: logistics, 活跃的铁路, pump truck placement and weather, 举几个例子. “All of this was done within a constrained project space,” said project team member Pat Naughton.  

“And we had to do it while keeping quality and the safety of all involved at top of mind,泰勒·沃克纳补充道, 另一名团队成员. “Collaboration and engagement was one of the biggest factors in making this portion of the project successful,他说.

foundation pouring during the day

Adding to the complexity were Iowa’s chilling winter temperatures, which required a special concrete thermal control plan and 24/7 monitoring.  

这仅仅是个开始.  

foundation pouring occurring at night
送出“五头大象”

建于林肯, 内布拉斯加州, the two natural gas boilers were the largest fully assembled boilers that could be transported via heavy hauler.  

包括24英尺宽的, 17英尺高的锅炉, the massive hauling unit totaled 220 feet and weighed approx. 620000磅. Due to the magnitude of the colossal load, extensive travel requirements were in place to ensure the safety of all involved. Permits were needed in every county and city they planned to travel through. 在总, the hauler would need to travel 700 miles through three states, 两次, a journey that required a police escort and lifted power lines.

“The feat of this part of the project was massive. To ship something that is that heavy over the road, takes a large amount of engineering. It was eye-opening once you start diving into the details of how much coordination is required to make sure it’s going to be safe for all parties,托尼·克利夫斯说, 项目经理.

After a 12-day journey, the first boiler arrived at the mill on March 19. The team then did it all again, and the second boiler was delivered on April 5.

delivery route map for the boiler project
进入位置

一旦现场, the team disassembled the transport, rotated the boilers and prepared them for the short journey to the project site.

This is a once in a lifetime opportunity. Not just for the project team, but for the mill as a whole.

An 80-wheeled goldhofer – a hydraulic modular platform trailer driven by remote control and used for heavy transportation – moved the boilers to the project grounds. 以步行速度行进, it took less than 30 minutes for crews to move the boilers, watching carefully to ensure levelness of the 24-foot-tall load. A crane was used to lift and lower them into their final resting places.  

Over the past year, the mill has been buzzing about this project. “This is a once in a lifetime opportunity. Not just for the project team, but for the mill as a whole,” said Tony. “Many of the mill employees are on the project team and we’ve incorporated a large number of team members into the project overall. People are informed, they are involved, and that tends to lead to more excitement.”

完成锅炉
展望未来

Once this project is complete at the end of 2025, the mill’s emissions will be reduced by approximately 25% as a result of the replacement of the coal-based steam currently used. 这将有助于我们的 2030年愿景 target of reducing our enterprise greenhouse gas emissions by 35% by year 2030. You can read more about it in our 可持续发展报告.

"The main building structural steel will start being erected in June, said Tony. “We have a lot more to go, but this is a great milestone to have behind us.”